"Plumbers started the rough in yesterday and did not finish. They cannot get me back on schedule until 2/4. I am very frustrated with my plumbers currently. This is not how we do things. I am working to get them in prior to that date. I am working with my area manager and the owner of the plumbing company to get this job completed. I am sorry and I now this isn’t what you wanted to hear this afternoon. Hopefully I will have better news for you next week."
Needless to say, Dave and I were very disappointed with this update. Dave and Shawn communicated (much more eloquently that I ever could) and Shawn is confident that this time will be made and and ultimately won't change our anticipated completion date.31 January 2021
Shawn Says...Part 9
24 January 2021
Shawn Says...Part 8
"Plumbers are confirmed for 1/25-26. Electrical rough in will follow on 1/27-28. Inspections for both will happen once each trade has completed. Framing inspection will take place after rough ins pass inspection."
So not much happened this past week and we saw no changes when we visited he house today. Jack suggested we have a picnic in the house so Dave and I joined him for a rather chilly picnic in our new house. Sam and Kate decided to stay warm at home with Ge-Ge.
Enjoying a chilly picnic in our dining room. |
We are getting a three seat sofa, a two seat love seat, and a recliner like this. |
This table has a leaf to make it larger and can easily seat 6 people. |
These are a sample of the stains we will use for our table, chairs and sideboard. |
Our sideboard will be the grey stain. |
17 January 2021
Shawn Says...Part 7
"Mechanical rough in has been completed. Inspection will take place next week. Plumbers are on schedule 1/25-26. They are currently behind due to Covid. They have a few crews sidelined currently. Electrical rough will take place once plumbers have completed."
This is the final design of our house. Ours is elevated a bit so we have steps leading to the front door. |
The current state of the exterior. We have windows and exterior doors installed. |
Some of the duct work in the laundry room |
Duct work at the top of the stairs |
Duct work in the attic space |
This is the pocket park that is across the street and just a few doors down from our house. |
Best news of all: Elizabeth's dear childhood friend, Marisa and her family are moving in two doors down! |
11 January 2021
Shawn Says...Part 6
"We are ready for rough ins. Plumbers have walked the home to be sure all there needs are met. They are on schedule for 1/20. My mechanical crew is on schedule for Monday and Tuesday. Once they are completed I will have the inspection scheduled. We will have a little time before the plumbers. We are ahead of schedule and I couldn’t move the plumber up. Electricians will follow the plumbers."
Looking from the living room toward the front door and Dave's office |
Looking toward the living room and dining room |
The game room |
Jack's room! |
at Sam who is looking down from the second floor. |
03 January 2021
Shawn Says...Part 5
"Framing will be completed by Monday. My crew is cleaning up odds and ends. Shingles installed today. Windows and exterior doors are on schedule for Monday. Trades will begin rough ins at the end of the week.
View into the living room and fireplace |
Jack in Ge-Ge's room
|
Up the Stairs |
Down the stairs |
Kate's room |
A heart cut into the window of the master bathroom |
Master bedroom/owner's retreat |
Middle of the upper floor looking into the master bedroom |
Sam's Room |
Jack's room |