15 February 2021

Shawn Says...Part 11

"All trades have completed rough ins and passed inspections! Framing inspection will take place on Tuesday. Inspections department isn’t working Monday. Insulation and insulation inspection will take place once we get past framing inspection. We have been experiencing insulation delays due to Covid. I am hoping to beat the delay by schedule three days ahead of when we need it installed. Will see if I can time it just right."

Yay! It was nice to get some good news in our weekly update! We had already seen the plumbing that went in but this week we saw a lot of the electrical work has begun as well!


Electrical wires for our outdoor garage lights and an outlet (I guess)


Some insulation around the a/c ducting



Our electric meter box has been installed but the power is
still in its temporary home in the front yard


Main sewer line and some sort of pressure gage 


Power outlet for the screened porch


Water and power for the kitchen island


Insulated plumbing


I don't know what the hell this is but it looked important


Electrical switch boxes


More electrical switch boxes


Fuse box



More plumbing that has been insulated


Windows have been insulated


Jack also made a video this week of the house progress. He got a "green screen" for Valentine's Day and he is putting it to good use!





No comments: