29 March 2021

Shawn Says...Parts 16 & 17

 Okay, okay, okay! I didn't post last week (and I heard about it from a few people) so now you get two updates in one!

March 21st:

"Painters will be completed today. Bath and kitchen top will be installed on Monday. Tile will begin on Tuesday and take the rest of the week to complete. Hoping for better weather next week to knockout driveway and sidewalk."





March 28th:

"Prime and paint have been completed. Tile for the floors and walls completed today. Backsplash tile is on schedule for Monday. Trades will begin trim outs late next week."


The beginning of a sidewalk!



I noticed the porch "columns" are painted!


We have a garage door!


The garage from inside the house


Kitchen!


The island makes me happy!


Where the dishwasher will go


Ge-Ge's bathroom



Master bathroom


Boys' bathroom


Kate's bathroom












14 March 2021

Shawn Says...Part 15

"Cabinets have been installed. Trim and doors have also been installed this week. Prime and first paint started on Thursday. Paint takes five days to completed and then tile will be installed."

What an exciting visit we had today! Everything is really coming together and it's so fun to watch. Sadly, I feel like our weekly sneaky visits will be coming to an end soon as they will start locking the doors to protect the finishings.


Kitchen cabinets are in!



Pantry shelving


Drop zone


Windows all have trim now


The mantel 


Office doors


Kate being Queen of the Porch



Bannisters and railings are on the stairs


Master bath


Boy's bathroom



Sam's room toward his closet



Double doors to the game room




07 March 2021

Shawn Says...Part 14


"Stone veneer was completed week. Drywall was completed today. Cabinets have been delivered and will be installed Monday. Trim and interior doors will be installed on Tuesday/Wednesday. Prime and first paint will start on Thursday." 


It was another productive week of work on the house. It's really starting to come together and feel like a real house. We are excited to see the updates coming up, too. Hopefully, we will get our official closing date soon!


We love the stonework!

Details of the columns






Stonework by the front door


Shutters, siding and stonework on
the front porch

Porch steps

Stonework detail around the garage

Drywall in the garage

Columns on the screened porch

Crawl space door has been installed

The cabinets are here!

More cabinets

Even more cabinets upstairs

Our cabinets will be stone grey

Master bedroom

Upstairs hallway

Kate's room

Corners and edges seem to have been 
prepped for painting





28 February 2021

Shawn Says...Part 13


"My drywall crew is still working on your home. The final day of drywall is next Friday. Cabinets will be installed the follow week. Siding has been completed and my mason has started the stone veneer prep today."

Update #13 seems to have been a lucky one for us. It was so fun to go over to the house and see all of the new updates! It's really starting to feel like a house now. The kids are a little bummed that they can't walk through the walls like ghosts anymore, but I am happy to see real walls up!


Front of the house with siding completed

Siding completed on the back side of the house.

Insulation on the ceiling of the screened in porch
(which is under the master bedroom)

Stonework on the edge of the front porch

Front steps have stone!

Kitchen

Breakfast nook

Dave admiring the work

Living room

From the living room toward the front door

Dave's office

Ge-Ge's bathroom

Up the stairs

Loft area at the top of the stairs (how should we use this space?)

Laundry room

Tray ceiling in the master bedroom

Master bathroom shower

Jack's room

Sam's room

Kate's room

Game room

Kids demonstrating the game room

Attic access